Your unit
Resident
Bldg B · 201
Theresa Quinn · 142 Maple Ridge Dr · #201
Current phase
ACTIVE · week 2
Roof tear-off complete on your unit. New underlayment installed. Final roofing material scheduled this week.
Latest notices for you
📌 Water shut-off · Tue 5/14 · 9 AM – 3 PM
important2026-05-12 19:34:31
Heads up: water will be off in Bldg B on Tuesday May 14 from 9 AM to 3 PM while we tie in the new flashings. Please fill a pitcher beforehand if needed. Crew lead Marcus is reachable at the contact below if anything comes up.
Progress update · Week 2
normal2026-05-12 19:34:31
Roof tear-off complete on units 201 and 202. New underlayment installed and weather-sealed. Photos available in your portal. Units 204 and 206 scheduled for Thursday and Friday this week.
Photos of your unit
3 photos · each one taken after a QR scan at your door.