Building B · roof replacement

Week 2 of 6 · 2/4 units complete

Board member

Schedule

Started May 5Est. complete Jun 12

On schedule. Next milestone: units 204 & 206 tear-off Thu/Fri.

Budget

$48,200 drawn$263,800 remaining

Of approved $312,000 reserve. Next draw request due Friday.

View draw schedule

Residents

4 units4 active

Channels: 2 email · 1 SMS · 1 paper

See all units

Recent evidence

Crew arrival · roof tear-off start
QR verifiedUNIT 1

Crew arrival · roof tear-off start

Marcus J. · 2026-05-12 19:34:31

Old shingles removed · underlayment exposed
QR verifiedUNIT 1

Old shingles removed · underlayment exposed

Marcus J. · 2026-05-12 19:34:31

New underlayment installed · weather-sealed
QR verifiedUNIT 1

New underlayment installed · weather-sealed

Marcus J. · 2026-05-12 19:34:31

Arrival · unit 202 · ready for tear-off
QR verifiedUNIT 2

Arrival · unit 202 · ready for tear-off

Diego A. · 2026-05-12 19:34:31

Drone overview · Bldg B southwest corner
QR verifiedUNIT 4

Drone overview · Bldg B southwest corner

Marcus J. · 2026-05-12 19:34:31

Recent notices

WhenTitleAudienceChannelsPriority
2026-05-12 19:34:31Reserve fund draw · interimboard_onlyemailinfo
2026-05-12 19:34:31Progress update · Week 2allemailnormal
2026-05-12 19:34:31Water shut-off · Tue 5/14 · 9 AM – 3 PMallemail · paperimportant